Rehabbing the TCB Road July to October

 

Caltrans

2019 Schedule for Caltrans Road Work on TCB 

In July, Caltrans is slated to begin work on a rehab pavement project on Topanga Canyon Boulevard. Please see attached details of scheduled work below. 

The work will take place on TCB (SR-27) between PCH and Cezanne Pl. (just south of Mulholland Dr.).

Please note that the initial date of completion for this contract is December 23, 2019. The contractor is anticipating completion of the work of this contract by mid-October 2019 as follows:



OPERATION                                            DATES

Construction Area Signs                             June 24, 2019, through July 5, 2019

AC Dig-Outs                                              July 8, 2019, through July 24, 2019

Shoulder Backing                                       July 22, 2019, through August 2, 2019

Crack Sealing and Striping Removal            August 5, 2019, through August 23, 2019

Slurry Seal                                                August 27, 2019, through September 14, 2019

Electrical Loops                                          September 19 & 20, 2019

Permanent Striping                                    September 23, 2019, through October 4, 2019

Remove Construction Area Signs                 October 7, 2019, through October 11, 2019

 